The Program Evaluation and Review Technique (PERT) is a widely used project management tool that helps project managers estimate the time and resources needed to complete a project. It is a valuable tool for planning and managing projects of all sizes and complexities.

PERT uses a weighted average of optimistic, pessimistic, and most likely time estimates to calculate the expected time for each task. This information is then used to create a project schedule that identifies the critical path, which is the sequence of tasks that must be completed on time in order to complete the project on time.
PERT also calculates the variance, which is a measure of the uncertainty associated with each task. This information can be used to identify tasks that are at risk of delay and to develop contingency plans.
Checking PERT scores regularly is essential for ensuring that a project is on track. If the PERT scores start to deviate from the original plan, it is important to take corrective action. This may involve adjusting the project schedule, allocating additional resources, or changing the scope of the project.
Benefits of Checking PERT Scores Regularly
There are many benefits to checking PERT scores regularly. Some of the most important benefits include:
- Improved project planning: PERT scores can help project managers to identify the critical path and to allocate resources accordingly. This can help to reduce the risk of delays and to ensure that the project is completed on time.
- Reduced project costs: PERT scores can help project managers to identify tasks that are at risk of delay. This information can be used to develop contingency plans and to avoid costly delays.
- Increased project quality: PERT scores can help project managers to identify tasks that are critical to the success of the project. This information can be used to ensure that these tasks are completed on time and to a high standard.
- Improved stakeholder satisfaction: PERT scores can help project managers to keep stakeholders informed about the progress of the project. This can help to build trust and to ensure that stakeholders are satisfied with the project outcome.
How to Check PERT Scores
Checking PERT scores is a relatively simple process. The following steps will help you to check PERT scores:
- Identify the tasks that are critical to the success of the project.
- Estimate the optimistic, pessimistic, and most likely time for each task.
- Calculate the expected time for each task using the following formula:
Expected time = (Optimistic time + 4 * Most likely time + Pessimistic time) / 6
- Calculate the variance for each task using the following formula:
Variance = (Pessimistic time - Optimistic time) / 6
- Create a project schedule that identifies the critical path.
- Monitor the progress of the project regularly and compare the actual progress to the PERT scores.
- Take corrective action if the PERT scores start to deviate from the original plan.
Common Mistakes to Avoid
There are a few common mistakes that should be avoided when checking PERT scores. These mistakes include:
- Not checking PERT scores regularly: PERT scores should be checked regularly, especially if the project is complex or if there are any changes to the project scope.
- Not using accurate time estimates: The accuracy of PERT scores depends on the accuracy of the time estimates. It is important to use realistic time estimates and to take into account the uncertainty associated with each task.
- Not calculating the variance: The variance is a measure of the uncertainty associated with each task. It is important to calculate the variance and to use this information to identify tasks that are at risk of delay.
- Not taking corrective action: If the PERT scores start to deviate from the original plan, it is important to take corrective action. This may involve adjusting the project schedule, allocating additional resources, or changing the scope of the project.
Conclusion
Checking PERT scores regularly is an essential part of project management. By checking PERT scores regularly, project managers can identify potential problems and take corrective action to ensure that the project is completed on time and within budget.
Additional Resources
- PERT Analysis: A Step-by-Step Guide
- How to Use PERT Charts to Plan and Manage Projects
- PERT Chart Template
Tables
Table 1: PERT Score Calculation
Task | Optimistic Time | Pessimistic Time | Most Likely Time | Expected Time | Variance |
---|---|---|---|---|---|
Task A | 2 days | 5 days | 3 days | 3.2 days | 0.5 days |
Task B | 1 day | 6 days | 3 days | 3.2 days | 1.3 days |
Task C | 3 days | 9 days | 5 days | 5.2 days | 1.3 days |
Table 2: Project Schedule
Task | Start Date | End Date | Duration |
---|---|---|---|
Task A | March 1 | March 3 | 2 days |
Task B | March 3 | March 9 | 6 days |
Task C | March 9 | March 15 | 6 days |
Table 3: Task Variance
Task | Variance |
---|---|
Task A | 0.5 days |
Task B | 1.3 days |
Task C | 1.3 days |
Table 4: Corrective Actions
PERT Score Deviation | Corrective Action |
---|---|
PERT score is higher than the original plan | Adjust the project schedule, allocate additional resources, or change the scope of the project. |
PERT score is lower than the original plan | Monitor the progress of the project closely and take corrective action if necessary. |